Get up to speed
The Devola Sanitary Sewer Improvements project, in compliance with Ohio EPA findings and orders, stating no discharge to surface waters will be allowed, involves the design and construction of a new central sanitary sewer to serve Phase II within the Ohio Environmental Protection Agency's (OEPA) defined service area. This proposed sanitary sewer will tie into the existing Phase I system, which flows downstream to the Devola lift station located at 4441 Hwy 60, south of Devola. This activity is following the court ordered mandate to comply with the OEPA Director's Final Findings and Orders.
Announcements
Installation of the majority of the sanitary sewer mains and laterals has been completed, and wastewater tank installation has begun, with a tank required at each home. A new interactive map linked to the right has been added to the website showing the order in which construction for the wastewater tanks will begin for groups of properties as well as when construction for that area has been completed.
Please note your installation area and plan accordingly. The project team will make every effort to provide advance notice. A response from the homeowner is requested so that proper coordination can take place.
All-Terrain Sewer Map and My Property
Engage with our interactive map! Enter your property address to view how your property will be connected to the system.
New!
Tank Installation Progress Map
Note: Exact order subject to change. Notice for your specific area will be placed on the front door prior to construction. Construction will commence in an orderly fashion from home to home along a given street. Please take note as construction approaches your home.
Restoration of disturbed areas will proceed immediately after installation with temporary seeding and mulching. Some settlement within the disturbed area may occur immediately after. The Contractor is required and will provide final restoration of all disturbed areas with final seeding and mulching as weather conditions allow. We request your patience as the project progresses.
Process
-
Surveying & Mapping
The project started with the field survey work which identified topographical details, located underground utilities, and provided ground elevations.
-
Design & Public Involvement
Design work and public involvement process consisted of three public involvement meetings scheduled for January and October of 2020 and November 2021. The goal of these meetings was to educate property owners about the project, the process, and the proposed alternatives; to gather property details; and to get feedback from property owners.
Preliminary plans (30%) were submitted April 2020 and finalized in October 2021.
-
Construction
Opening Bid - May 12, 2022
Contractor notice to proceed and construction to start late Summer 2022
Installation of all sanitary sewer mains completed October 2023
Completion of 280 homes by Spring 2024
Project completion October 2025
Schedule
-
Nov 27General Plan Submitted to OEPA
-
Jan 141st Public Meeting
-
Apr 142nd Public Meeting
Due to the Covid-19 outbreak and at the recommendation of the Governor's office, this public meeting was cancelled. -
Apr 21Submit Preliminary Plans (30%) to the Washington County Engineer's Office for review and approval
-
Jul 01Preliminary Plans Completed (30%)
-
Oct 06Virtual Public Meeting
-
Nov 2590% Design Plans submitted to the OEPA
-
Dec 15Final Design Submittal to Washington County
-
Jan 28Received comments from OPEA
-
Feb 26Resubmitted Design Plans to OPEA
-
Mar 10Received Permit to Install (PTI) Approval from OEPA
-
SpringFunding sources identified
-
SummerAdditional Funding sources identified causing delays to start of project
-
AugWashington County requested changes to Final Plans
-
SeptEasement and Maintenance Agreement Document Acquisition begins
-
NovRe-issued Plans sent to Agencies for Approval
-
Nov 16Public Meeting
-
DecAnticipated approval of re-ssued PTI
-
March 8Public Meeting
-
March 18OEPA Approval of Reissued PTI (Permit to Install)
-
March 29OEPA Preliminary Finding of No Significant Impact (FNSI)
-
March 31Advertisement/Invitation for Bidders to Bid on Construction
-
May 12Bid Opening
-
June 2DPC Contractors to begin contacting homeowners
-
June 6DPC Contractors to begin evaluations of residents' current electrical status
-
Mid-JuneDPC Contractors to begin Priority 1 electrical work
-
Late SummerNotice to proceed with Construction
-
WinterDPC Contractors to complete electrical upgrades
-
FallInstallation of sewer mains completed
-
SpringCompletion of 280 homes
-
OctoberCompletion of project
Location
Documents
- Revised Project Schedule
- Washington County Ea Public Notice Of Finding Of No Significant Impact
- Washington County Low-Pressure Sewer User's Manual
- Oct. 6, 2020 Virtual Public Meeting Event and Materials
- Oct. 6, 2020 Virtual Public Meeting Flyer
- Resident Survey
- General Plan
- Public Involvement 1 Notification